3.1 Post Construction Activities |
| |
|
| |
3.1.1 Conduct
Contractor Performance Evaluation
Construction Management Representative (CMR) -
- Provides input for the Contractor
Performance System, construction evaluation of the contractor.
You will be given an ID and password to input the information
directly into the system.
Templates:
Samples:
Back to top ^ |
| |
|
| |
3.1.2 Prepare
Draft Completion Reports (Fixed Assets)
CMR -
- Prepare Draft Completion Report (Form 10-174, Narrative statement, Photos, 10-174A) and draft transmittal letter after all work is completed
and contractor has signed all modifications. Send draft completion report and letter to COR for review.
- Incorporate COR comments and send transmittal letter to Park
Superintendent with one copy of Draft Completion Report.
- Forward park-signed transmittal letter and two copies
of Draft Completion Report to COR.
Guidelines:
Templates:
Samples:
Back to top ^ |
| |
|
| |
3.1.3 Demobilize Field Office
CMR -
- Contact local utilities (electric, telephone, propane)
and long distance telephone companies to schedule disconnection
of services (after completion of punch list work, before
removal of construction trailer)
- Clean out files, retain any original document(s) and forward to the Contracting Officer Representative (COR), and discard duplicate
files. Duplicate files with sensitive information shall be shredded or otherwise destroyed.
- If you have construction contractor supplied computer,
copy all project
files
to a CD and remove project files from the hard drive, securely
delete (wipe) contract files from hard drive.
Forward CD to COR. Return computer to contractor.
- Ensure that all material samples, spare tools, parts,
submittals, and other project closeout items have been turned
over to the park; all unused contractor-supplied materials
and equipment should remain in trailer
- Return trailer to same condition as when first occupied,
less normal
wear and tear
- Return trailer keys to contractor
Back to top ^ |
|
|