square bullet 3.1 Post Construction Activities
 
 

3.1.1 Conduct Contractor Performance Evaluation

Construction Management Representative (CMR) -

  • Provides input for the Contractor Performance System, construction evaluation of the contractor. You will be given an ID and password to input the information directly into the system.

Templates:

Samples:

Back to top ^

 
 

3.1.2 Prepare Draft Completion Reports (Fixed Assets)

CMR -

  • Prepare Draft Completion Report (Form 10-174, Narrative statement, Photos, 10-174A) and draft transmittal letter after all work is completed and contractor has signed all modifications. Send draft completion report and letter to COR for review.
  • Incorporate COR comments and send transmittal letter to Park Superintendent with one copy of Draft Completion Report.
  • Forward park-signed transmittal letter and two copies of Draft Completion Report to COR.

Guidelines:

Templates:

Samples:

Back to top ^

 
  3.1.3 Demobilize Field Office

CMR -

  • Contact local utilities (electric, telephone, propane) and long distance telephone companies to schedule disconnection of services (after completion of punch list work, before removal of construction trailer)
  • Clean out files, retain any original document(s) and forward to the Contracting Officer Representative (COR), and discard duplicate files. Duplicate files with sensitive information shall be shredded or otherwise destroyed.
  • If you have construction contractor supplied computer, copy all project
    files to a CD and remove project files from the hard drive, securely
    delete (wipe) contract files from hard drive. Forward CD to COR. Return computer to contractor.
  • Ensure that all material samples, spare tools, parts, submittals, and other project closeout items have been turned over to the park; all unused contractor-supplied materials and equipment should remain in trailer
  • Return trailer to same condition as when first occupied, less normal
    wear and tear
  • Return trailer keys to contractor

Back to top ^

Pre - Construction
Construction
Post Construction
bullet Post Construction Activities
    Conduct Contractor Performance Evaluation
    Prepare Draft
Completion Reports
    Demobilize Field Office
 
Information
DSC Workflows Definitions
Forms / Templates /
Samples / Guidelines
Laws and Policies
Photo Gallery
bullet What's New

Site Map | Contact | | Disclaimer | FOIA | US Department of Interior | USA.gov | ParkNet | DSC