2.24 Final Inspection

Construction Management Representative (CMR) -

  • Coordinate with contractor, park, and COR to set final inspection date
  • Draft and sign response letter to contractor providing final inspection date using template below.
  • Conduct final inspection and incorporate a final sequentially numbered, priced punch list into the draft letter of substantial completion; and send electronic version to COR
  • Before occupancy can occur on building projects the Regional Structural Fire Management Officer (RSFMO) has to have accepted the fire and life safety systems and issued a preliminary certificate of occupancy. Utilize forms below as required.

Guidelines:

Forms:

Templates:

Back to top ^


square bullet 2.25 Completion of Punch List Items

CMR -

  • Monitor contractor's progress on punch list completion and maintain an updated priced punch list
  • Notify COR upon completion of punch list work

square bullet

2.26 As-Built Drawings

CMR -

  • Perform final review of as-built drawing submittal for completeness and accuracy (see Division 1 section 01770, Project Record Drawings); forward 2 copies to COR and one copy to park, chief of maintenance

Back to top ^


square bullet 2.27 Required Training Provided

CMR -

  • Verify all training requirements are shown in the Closeout and Operations & Maintenance requirements checklist included at the end of Division 1 Specifications.
  • Verify what training has or has not been provided
  • Coordinate with the contractor to schedule and complete the remainder

square bullet

2.28 Spare Parts, Replacement Materials, Tools, Etc.

CMR -

  • Verify all requirements are shown in the Closeout and Operations
    & Maintenance requirements checklist included at the end
    of Division 1 Specifications.
  • Perform inventory of what has been furnished
  • Ensure that all omissions are covered in the punch list
Pre-Construction
Construction
bullet Submittals
bullet Construction Activities
bullet Construction Modifications
bullet Closeout Submittals
bullet Substantial Completion
    Final Inspection
    Completion of Punch List Items
    As-Built Drawings
    Required Training Provided
    Spare Parts, Replacement Materials, Tools, Etc.
Post Construction
     
Information
bullet DSC Workflows Definitions
bullet Forms / Templates / Samples / Guidelines
bullet Laws and Policies
bullet Photo Gallery
bullet What's New

Site Map | Contact | | Disclaimer | FOIA | US Department of Interior | USA.gov | ParkNet | DSC