2.3 Coordinate with Utility Companies
Construction Management Representative (CMR) -
- Review contract documents and determine whether government or contractor
has responsibility to coordinate and provide/pay for temporary
and permanent utility
connections
- Coordinate this work with the Park, verify proper inspections are
performed to ensure
connections downstream or upstream meet code/requirements; if
necessary, initiate letter to utility
company, signed by Project Manager (PM)
Guidelines:
Document Control:
|
| |
|
|
 |
2.4 Coordinate with Harpers Ferry Center
CMR -
- Ensure coordination with all parties including distributing copies
of memos to all parties, e-mail,
sketches, etc., impacting exhibitry, keeping record copy of
all correspondence
- Make contact with Exhibit Specialist at start of construction, and coordinate
with work
in progress, such as electrical rough-in, rough carpentry, cabinetry, and
any work
impacting the Harpers Ferry
Center design, or as requested by the Exhibit Specialist
Back to top ^ |
| |
|
 |
2.5 Coordinate with Park and Concessionaires
CMR -
- Share information and ensure coordination with
all parties, keep
record file of all correspondence, update
representative on work progress, modifications, safety
fire issues, traffic controls, and other items as needed.
Guideline:
|
|
|
|
 |
2.6 Progress Meetings
CMR -
- Convene progress meetings on weekday and time
agreed upon at pre-construction conference
- Conduct meeting
using agenda (see Spec 01310), and ensure minutes are taken and routed promptly
Template:
Sample:
Document Control:
- Electronic copy of meeting minutes are routed to Park Superintendent, Project Manager,
COR, CMR, Contract Specialist (CS)
Back to top ^ |
|
|
 |
2.7 General
Correspondence Procedures
- All correspondence signed by CMR should be on the
construction management firm's official stationary
- Follow DSC
Correspondence Guidelines for official correspondence
|
|
|
|
 |
2.8 Payrolls
CMR -
- Enforce submittal of payrolls by contractor with
statement of compliance (Form
WH-347, page 2)
- Forward payrolls,
once a month, with corresponding daily reports and labor
interviews (see Labor Standards Interviews) to DSC
Contract Specialist
Guidelines:
Forms:
- 2.8C WH347 (Statement of Compliance)
(The contractor has the option of using this form or your
own form. If you choose to use your own form, it must, at
a minimum, contain the same information shown on this form.)
Back to top ^ |
|
|
|
|
 |
2.9 Contractor Quality Control (CQC), Daily Diaries
CMR Daily Diaries -
- Complete daily diaries and forward them to the COR on a weekly basis
CQC Reports -
- CMR will receive/review/note discrepancies/forward
Daily Diaries, with attachments (Daily Test Reports, CQC Accessibility Inspection Reports), to COR
Forms:
Sample:
- 2.9E CQC Assessibility Inspection Report Sample - Under Construction
Back to top ^ |
|
|
|
|
 |
2.10 Critical Point and Milestone
Inspections
CMR -
- Notify COR of milestones and recommend necessary personnel,
including
utility providers, A/E design, NPS, etc., to be in attendance
and coordinate critical inspections (systems, start-ups,
demonstrations,
etc.)
- Facilitate preparatory/initial/follow-up inspections
- Document findings
in Daily Diary
|
|
| |
|
|
 |
2.11 Rejected Work
CMR -
- Inspect ongoing construction, identify deficiencies in construction, materials
and/or project progress, and verbally inform CQC of deficiencies (FAR
52.246-12 or 52.236-5)
- For non-compliant work, point out specific contract requirements
that are not being met.
- If work is not corrected in a timely manner, draft a Rejection
letter for the COR to sign.
- Inspect the contractor's corrected work, and document results
in
the daily diary
Guideline:
Template:
Sample:
Back to top ^ |
|
|
|
|
 |
2.12 Project Photographs
CMR -
- Photos are taken of existing conditions before commencement
of each major phase of work, unacceptable or disputed portions
of the work, subsurface conditions,
progress and workforce/equipment, work to be covered, rejected work, safety
issues, and completed phase and/or project
- Progress photos (minimum
of three) shall be e-mailed to the COR
on a weekly basis
- Label
all media to show park, package number, contract number, project
title, date, photographer, and explanation of the subject
(See templates below – alternate
log will be acceptable provided the same information is conveyed)
- Archive
project photos, saved as *.jpg files, utilizing recordable
CD-ROM drive; forward all CD-ROM disks of digital photos
to COR at end of project
Templates:
|
|
|
|
|
 |
2.13 Progress Payments
CMR -
- Conduct quantity survey with contractor to document
quantities for the monthly
pay record
- Receive contractor's draft monthly Pay Estimate form, Schedule
of
Values back-up, and updated progress schedule, certification
form (FAR 52.232-5)
- Review pay estimate form and reaches
agreement with contractor on quantities, percent complete
and payment due
Note:
— for unit price items, pay actual installed and accepted
quantities only.
— for lump sum items, agree on a percent complete based on the schedule
of value breakdown
- Inform contractor of any missing back-up that
must be provided with final invoice to allow processing and they are responsible for incorporating changes and sending to the contracts office at DSC.
- Fax, scan or email marked-up draft pay estimate form and checklist
to COR
Guidelines:
Templates:
Sample:
Back to top ^ |
|
|
|
|
 |
2.14 Labor Standards Interviews
CMR -
- Conduct periodic interviews with workers on the
job (interviews each new trade as a new phase of work is started
by the contractor or a subcontractor) using
Labor Standards Interview Form (SF-1445)
- Complete "INTERVIEWER'S COMMENTS" portion of Labor
Standards Interview form by checking against submitted payroll
data; sign, date,
and attach Labor
Standards Interview form to the respective payroll
report for the period
covered by interview and forward to Construction CS.
If discrepencies are found, immediately notify the CS and COR.
(FAR
52.222-8)
- Ensure that interviews cause as little disruption
as possible to the on-going work; ensure information gathered by means of interview is kept in strict
confidence and not disclosed to worker's employer unless specific authorization
is obtained in writing from Contracting Officer
Guideline:
Template:
- 2.14B SF-1445, Labor Standards Interview blank form
|
|
|
|
|
 |
2.15 Miller Act Response
CMR -
Back to top ^ |
|
|
|
 |
2.16 Accident Reporting
CMR -
- Obtain a completed DSC Contractor Accident/Property
Damage Report
(Form
CM-22)
from the contractor and forward to COR
Template:
- 2.16A Form
CM-22 DSC - Contractor Accident/Property
Damage Report
|
|
|
|
 |
2.17 Request for Information (RFI)
CMR -
- Enter RFI in log and contact A/E Designer, COR, as necessary,
to obtain information
- Ensure that RFI comments
are sent back to the contractor in a timely manner
- Clear all RFIs up as soon as possible. Prioritize if necessary
to provide immediate resolution to RFIs that will cause time and
money impacts.
- Enter the return date in the log
- If RFI cannot be answered with information contained within
the contract documents, refer to contract modifications
Guideline:
Templates:
- 2.17B RFI Log
- 2.17C Request for Information Form
(The contractor has the option of using this form or your own form. If you choose to use your own form, it must, at a minimum, contain the same information shown on this form.)
Sample:
Back to top ^ |
|
|
|
|
 |
2.18 Beneficial Occupancy Inspection
CMR -
- Coordinate with contractor, park, and COR to determine who should be in attendance and sets
the Beneficial Occupancy
inspection
date.
- Conduct final inspection and Final Accessibility Inspection of that portion of the facility
covered in the beneficial occupancy request
- Generate priced punch list
- Draft Beneficial Occupancy Inspection letter and forward
electronic
copy to COR
- Monitor punch list completion and notify COR when completed
- Before occupancy can occur on building projects the Regional Structural Fire Management Officer (RSFMO) has to have accepted the fire and life safety systems and issued a preliminary certificate of occupancy. Utilize forms below as required.
Guidelines:
Forms:
Template:
Sample:
|
|
|
 |
2.19 Pre-Final Punch List
CMR -
- As contractor nears project completion, generate a preliminary
punch list; update as required until final inspection
Note: the objective is to have a minimal punch list for the
final inspection.