2.3 Coordinate with Utility Companies

Construction Management Representative (CMR) -

  • Review contract documents and determine whether government or contractor has responsibility to coordinate and provide/pay for temporary and permanent utility connections
  • Coordinate this work with the Park, verify proper inspections are
    performed to ensure connections downstream or upstream meet code/requirements; if necessary, initiate letter to utility company, signed
    by Project Manager (PM)

Guidelines:

Document Control:

 
square bullet 2.4 Coordinate with Harpers Ferry Center

CMR -

  • Ensure coordination with all parties including distributing copies of memos to all parties, e-mail, sketches, etc., impacting exhibitry, keeping record copy of all correspondence
  • Make contact with Exhibit Specialist at start of construction, and coordinate with work in progress, such as electrical rough-in, rough carpentry, cabinetry, and any work impacting the Harpers Ferry Center design, or as requested by the Exhibit Specialist

Back to top ^

 
square bullet 2.5 Coordinate with Park and Concessionaires

CMR -

  • Share information and ensure coordination with all parties, keep
    record file of all correspondence, update representative on work
    progress, modifications, safety fire issues, traffic controls, and other
    items as needed.

Guideline:


square bullet 2.6 Progress Meetings

CMR -

  • Convene progress meetings on weekday and time agreed upon at pre-construction conference
  • Conduct meeting using agenda (see Spec 01310), and ensure minutes are taken and routed promptly

Template:

Sample:

Document Control:

  • Electronic copy of meeting minutes are routed to Park Superintendent, Project Manager, COR, CMR, Contract Specialist (CS)

Back to top ^


square bullet 2.7 General Correspondence Procedures
  • All correspondence signed by CMR should be on the construction management firm's official stationary
  • Follow DSC Correspondence Guidelines for official correspondence

square bullet 2.8 Payrolls

CMR -

  • Enforce submittal of payrolls by contractor with statement of compliance (Form WH-347, page 2)
  • Forward payrolls, once a month, with corresponding daily reports and labor interviews (see Labor Standards Interviews) to DSC Contract Specialist

Guidelines:

Forms:

  • 2.8C WH347 (Statement of Compliance)
    (The contractor has the option of using this form or your own form. If you choose to use your own form, it must, at a minimum, contain the same information shown on this form.)

Back to top ^


square bullet

2.9 Contractor Quality Control (CQC), Daily Diaries

CMR Daily Diaries -

  • Complete daily diaries and forward them to the COR on a weekly basis

CQC Reports -

  • CMR will receive/review/note discrepancies/forward Daily Diaries, with attachments (Daily Test Reports, CQC Accessibility Inspection Reports), to COR

Forms:

Sample:

  • 2.9E CQC Assessibility Inspection Report Sample - Under Construction

Back to top ^


square bullet 2.10 Critical Point and Milestone Inspections

CMR -

  • Notify COR of milestones and recommend necessary personnel,
    including utility providers, A/E design, NPS, etc., to be in attendance
    and coordinate critical inspections (systems, start-ups,
    demonstrations, etc.)
  • Facilitate preparatory/initial/follow-up inspections
  • Document findings in Daily Diary
 
square bullet 2.11 Rejected Work

CMR -

  • Inspect ongoing construction, identify deficiencies in construction, materials and/or project progress, and verbally inform CQC of deficiencies (FAR 52.246-12 or 52.236-5)
  • For non-compliant work, point out specific contract requirements that are not being met.
  • If work is not corrected in a timely manner, draft a Rejection letter for the COR to sign.
  • Inspect the contractor's corrected work, and document results in
    the daily diary

Guideline:

Template:

Sample:

Back to top ^


square bullet 2.12 Project Photographs

CMR -

  • Photos are taken of existing conditions before commencement of each major phase of work, unacceptable or disputed portions of the work, subsurface conditions, progress and workforce/equipment, work to be covered, rejected work, safety issues, and completed phase and/or project
  • Progress photos (minimum of three) shall be e-mailed to the COR
    on a weekly basis
  • Label all media to show park, package number, contract number, project title, date, photographer, and explanation of the subject (See templates below – alternate log will be acceptable provided the same information is conveyed)
  • Archive project photos, saved as *.jpg files, utilizing recordable CD-ROM drive; forward all CD-ROM disks of digital photos to COR at end of project

Templates:


square bullet 2.13 Progress Payments

CMR -

  • Conduct quantity survey with contractor to document quantities for the monthly pay record
  • Receive contractor's draft monthly Pay Estimate form, Schedule of
    Values back-up, and updated progress schedule, certification form
    (FAR 52.232-5)
  • Review pay estimate form and reaches agreement with contractor on quantities, percent complete and payment due

    Note:
    — for unit price items, pay actual installed and accepted quantities only.
    — for lump sum items, agree on a percent complete based on the schedule of value breakdown
  • Inform contractor of any missing back-up that must be provided with final invoice to allow processing and they are responsible for incorporating changes and sending to the contracts office at DSC.
  • Fax, scan or email marked-up draft pay estimate form and checklist
    to COR

Guidelines:

Templates:

Sample:

Back to top ^


square bullet

2.14 Labor Standards Interviews

CMR -

  • Conduct periodic interviews with workers on the job (interviews each new trade as a new phase of work is started by the contractor or a subcontractor) using Labor Standards Interview Form (SF-1445)
  • Complete "INTERVIEWER'S COMMENTS" portion of Labor Standards Interview form by checking against submitted payroll data; sign, date,
    and attach Labor Standards Interview form to the respective payroll
    report for the period covered by interview and forward to Construction CS.
    If discrepencies are found, immediately notify the CS and COR.
    (FAR 52.222-8)
  • Ensure that interviews cause as little disruption as possible to the on-going work; ensure information gathered by means of interview is kept in strict confidence and not disclosed to worker's employer unless specific authorization is obtained in writing from Contracting Officer

Guideline:

Template:

  • 2.14B SF-1445, Labor Standards Interview blank form

square bullet 2.15 Miller Act Response

CMR -

Back to top ^


square bullet 2.16 Accident Reporting

CMR -

  • Obtain a completed DSC Contractor Accident/Property Damage Report
    (Form CM-22) from the contractor and forward to COR

Template:

  • 2.16A Form CM-22 DSC - Contractor Accident/Property Damage Report

square bullet 2.17 Request for Information (RFI)

CMR -

  • Enter RFI in log and contact A/E Designer, COR, as necessary, to obtain information
  • Ensure that RFI comments are sent back to the contractor in a timely manner
  • Clear all RFIs up as soon as possible. Prioritize if necessary to provide immediate resolution to RFIs that will cause time and money impacts.
  • Enter the return date in the log
  • If RFI cannot be answered with information contained within the contract documents, refer to contract modifications

Guideline:

Templates:

  • 2.17B RFI Log
  • 2.17C Request for Information Form
    (The contractor has the option of using this form or your own form. If you choose to use your own form, it must, at a minimum, contain the same information shown on this form.)

Sample:

Back to top ^


square bullet 2.18 Beneficial Occupancy Inspection

CMR -

  • Coordinate with contractor, park, and COR to determine who should be in attendance and sets the Beneficial Occupancy inspection date.
  • Conduct final inspection and Final Accessibility Inspection of that portion of the facility covered in the beneficial occupancy request
  • Generate priced punch list
  • Draft Beneficial Occupancy Inspection letter and forward electronic
    copy to COR
  • Monitor punch list completion and notify COR when completed
  • Before occupancy can occur on building projects the Regional Structural Fire Management Officer (RSFMO) has to have accepted the fire and life safety systems and issued a preliminary certificate of occupancy. Utilize forms below as required.

Guidelines:

Forms:

Template:

Sample:


square bullet 2.19 Pre-Final Punch List

CMR -

  • As contractor nears project completion, generate a preliminary punch list; update as required until final inspection
    Note: the objective is to have a minimal punch list for the final inspection.

Back to top ^

Pre-Construction
Construction
bullet Submittals
bullet Construction Activities
  Coordinate with
Utility Companies
  Coordinate with
Harpers Ferry Center
  Coordinate with Park
and Concessionaires
  Progress Meetings
  General Correspondence Procedures
  Payrolls
  CM Daily Diaries
& CQC daily Reports
  Critical Point and
Milestone Inspections
  Rejected Work
  Project Photographs
  Progress Payments
  Labor Standards Interviews
  Miller Act Response
  Accident Reporting
  Request for Information (RFI)
  Beneficial Occupancy Inspection
  Pre-Final Punch List
 
bullet Construction Modifications
bullet Closeout Submittals
bullet Substantial Completion
Post Construction
Information
DSC Workflows Definitions
Forms / Templates/
Samples / Guidelines
Laws and Policies
Photo Gallery
bullet What's New

Site Map | Contact | | Disclaimer | FOIA | US Department of Interior | USA.gov | ParkNet | DSC