2.1 Material Submittal Review

Construction Management Representative (CMR) -

  • Review submittal list (Attached to Spec Sec 01330) for completeness and conformance to the technical specification requirements.
  • Review individual submittals for completeness.
  • If incomplete, return submittal to contractor
  • If complete, enter submittal log data on Transmittal Form (CM-16).  Log submittal into CM-17. Keep 1 copy. 
  • Follow the Submittal Review Process flowchart for submittal reviews done by the A/E designer.
  • CMR Review Process
    • If this is a CM-reviewed submittal, review submittal, comment and sign in "Recommended by" block within 3 days
    • Mail 3 copies to Submittal Management Specialist (SMS) at DSC
      within 3 days.  
    • You will receive one signed copy back from SMS; make a copy of the signed CM-16 with comments and combine with blank copy and keep for field copy.  Return original submittal with comments to the contractor.

Guidelines:

Templates:

Samples:

Back to top ^


bullet

2.2 Division 1 Submittals

COR and/or CMR

* NOTE: Division 1 Submittals are processed before the Pre-Construction conference is held. Refer to Section 1.0 for processing requirements.

  • Ensure that all documents required have been received, reviewed, and comments incorporated.
    Discuss any outstanding issues with the contractor and clarify any questions on the contract requirements or review comments.
  • All outstanding issues should be resolved before the Pre-Construction conference. If not, resolve all outstanding issues in a timely manner (utilize template letter to contractor accepting/rejecting documents)
  • Monitor the contractors compliance with all Division 1 submittals.
  • Verify that CQC Supervisor is the same person indicated in the project proposal.
  • Maintain an updated copy of the project schedule throughout the contract.  Monitor contractor's performance based on scheduled activities, resources on site vs. scheduled, and the timely execution of the work.

Back to top ^

Pre - Construction
Construction
bullet Submittals
    Material
Submittal Review
    Division 1 Submittals
bullet Construction Activities
bullet Construction Modifications
bullet Closeout Submittals
bullet Substantial Completion
Post Construction
 
Information
bullet DSC Workflows Definitions
bullet Forms / Templates / Samples / Guidelines
bullet Laws and Policies
bullet Photo Gallery
bullet What's New

Site Map | Contact | | Disclaimer | FOIA | US Department of Interior | USA.gov | ParkNet | DSC