2.1 Initiate Environmental
Assessment (EA) or Environmental
Impact Statement (EIS) Activities as Required
When directed, conduct
data collection, public
and agency scoping, public meetings, agency
consultations and other required activities.
|
|
 |
2.2 Design Concepts Assessment
Present and revise, as needed, site-integrated massing and architectural design concepts based on the Contextual Analysis and/or Project Program. NPS will verify that design concepts are in compliance with the completed Contextual Analysis Form and/or Project Program.
In consultation with NPS, choose Final Design Concepts for further development into Schematic Design Alternatives.
|
|
 |
2.3 Develop Schematic Design
Alternatives
Utilizing Final Design Concepts, develop a range (minimum of three) Schematic
Design Alternatives that meet all Project Program
requirements and do not exceed available construction funds. All alternatives shall be consistent
with the Council
on Environmental Quality Regulations.
Prepare Class
C Construction Cost Estimate for each Schematic Design
Alternative.
Samples: Class
C Construction Cost Estimate
Guidance: Cost Estimating Requirements Handbook |
|
 |
2.4 Prepare Draft EA or EIS
When directed, prepare draft EA or EIS document and related
compliance documentation (Biological
Assessment, Statement of
Findings for Wetlands and/or Floodplains), as required.
When directed, prepare draft Memorandum
of Agreement (MOA) or Programmatic
Agreement (PA) for State
Historic Preservation Officer (SHPO) / Tribal
Historic Preservation Officer (THPO) and, if necessary, Advisory
Council on Historic Preservation (ACHP).
When directed, facilitate informational public house / public meetings. |
|
 |
2.5 Conduct Value Based Decision-Making
Conduct Value
Analysis study to analyze
the Schematic Design Alternatives.
NPS will select the Schematic
Design Preferred Alternative based on the recommendations
of the Value Analysis study.
Prepare Value Analysis Report.
Templates: VA Templates
|
|
 |
2.6 Fully Develop Schematic
Design Preferred Alternative
Develop the Schematic
Design Preferred Alternative and prepare
the Basis of
Design Report in sufficient detail to provide adequate data for
preparation of the Class
B Construction Cost Estimate.
|
|
 |
2.7 Prepare Class B Construction Cost Estimate
Prepare the Class
B Construction Cost Estimate based on the Fully Developed Schematic
Design Preferred Alternative. Confirm that the project
cost is within available funds.
Samples: Class
B Construction Cost Estimate
Guidance: Cost Estimating Requirements Handbook |
|
 |
2.8 Prepare LEED™ Project
Checklist
Prepare LEED™ (Leadership
in Energy and Environmental Design) Project Checklist when
required.
Templates: LEED™ Project Checklist
|
|
 |
2.9 Prepare Cost Comparability Analysis
Prepare the Cost Comparability Analysis for a minimum of three similar built non-National Park Service projects.
Templates: Cost Comparability Analysis Worksheet |
|
 |
2.10 Schematic
Design Deliverables
|
| |
|
| |
2.10.1
|
Submit
100% Draft Schematic Design Documents for Review:
|
| |
|
| |
2.10.2
|
Resolve 100% Draft Schematic
Design Review Comments
Resolve all review comments and incorporate resolutions into
the Final Schematic Design Documents. Submit the Final Schematic
Design Documents and written responses to review comments, utilizing
the NPS review form, within 15 calendar days of receipt of comments.
|
| |
|
|
|
|
|
2.10.2.1
|
Prepare and Submit Development
Advisory Board (DAB) Support Documents
Prepare and submit the following DAB Support
Documents:
- Proposed Design Development and Construction Document Value
Analysis activities on remaining key decisions.
- Five or fewer graphics providing an overview of the project
in electronic format:
- Existing Conditions Plan - location plan
- Site Plan
- Building Plans for each level
- Building Elevations
- Building and Site Selections
- Information required to update the Environmental
Screening Form (ESF)
|
| |
|
|
2.10.3
|
Response Memorandum
Prepare and submit response memorandum, when required, to DAB
review questions within 15 calendar days of receipt of DAB comments.
|
| |
|

|
2.11
|
Compliance Deliverables
|
| |
|
|
2.11.1
|
Submit Draft Compliance Documents
for NPS Review
- EA or EIS
- Biological
Assessment, Statement
of Findings for Wetlands and/or Floodplains.
- MOA or PA
(review of compliance drawings and supportive narrative may
be required, see paragraph 3.5.1)
|
| |
|
|
2.11.2
|
Incorporate
NPS Comments and Revise Draft Compliance Documents for Public Distribution |
| |
|
|
| |
|
2.11.2.1 |
Incorporate NPS comments and revise EA
or draft EIS for public distribution. |
| |
|
|
| |
|
2.11.2.2 |
Release compliance document(s) for public
review. |
| |
|
| |
2.11.3 |
Analyze Public Comments |
| |
|
|
| |
|
2.11.3.1 |
EA - Address Public Comments |
| |
|
|
| |
|
|
2.11.3.1a |
Address public comments. |
| |
|
|
|
| |
|
|
2.11.3.1b |
Prepare and submit Finding
of No Significant Impact (FONSI), including responses to substantive
comments. |
| |
|
|
| |
|
2.11.3.2 |
EIS - Incorporate Public Comments and
Revise Draft EIS |
| |
|
|
| |
|
|
2.11.3.2a |
Work collaboratively with NPS to identify
substantive public comments. |
| |
|
|
|
| |
|
|
2.11.3.2b |
Incorporate public comments. |
| |
|
|
|
| |
|
|
2.11.3.2c |
Prepare and submit draft final EIS for
NPS review. |
| |
|
|
|
| |
|
|
2.11.3.2d |
Incorporate NPS comments and prepare final
EIS for public distribution. |
| |
|
|
|
| |
|
|
2.11.3.2e |
Release final EIS. |
| |
|
|
|
| |
|
|
2.11.3.2f |
Prepare Draft Record
of Decision (ROD)
for NPS review. |
| |
|
|
|
| |
|
|
2.11.3.2g |
Incorporate NPS comments and finalize
ROD. |
| |
|
|
|
| |
|
|
2.11.3.2h |
Distribute ROD to the public.
Back to top ^ |