1.1 Prepare Contextual Analysis (Not Required for Designated Historic Structures and Cultural Landscapes)
Document existing Building and Site Character using the Contextual Analysis Template.
Template: Contextual Analysis Template |
|
 |
1.2 Prepare Project Program
Using the PMIS Project
Statement and the Facility
Planning Model
(if applicable), as the basis for programming,
prepare Project
Program.
The Project Program includes a Site Analysis, A Site Program, and an Architectural Program.
|
|
 |
1.3 Complete Contextual Analysis Template (When Required)
Document proposed Building and Site Character using the Contextual Analysis Template. |
|
 |
1.4 Review Environmental
Screening Form
Working collaboratively with park, review the Environmental
Screening Form (ESF) to ensure consistency with project
program and identify any missing resource data. The ESF will
be updated by the National Park Service.
Template: Environmental
Screening Form
|
|
 |
1.5 Prepare Class
C Construction Cost Estimate
Based on Project Program, prepared in Paragraph 1.2, prepare an
independent Class
C Construction Cost Estimate.
Samples: Class
C Construction Cost Estimate
Guidance: Cost Estimating Requirements Handbook |
|
 |
1.6 Obtain Cost Comparability Data
Obtain Cost Comparability data for a minimum of three similar built non-National Park Service projects and prepare the Cost Comparability Data Checklist.
Template: Cost Comparability Data Checklist / Sample
|
|
 |
1.7 Prepare Scope and Cost Validation Documentation
Document all scope, functionality and cost variations relative to the PMIS
Project Statement and PMIS Class C Construction Cost Estimate. This requirement applies only to Line Item Construction Projects.
Template: Scope and Cost Validation Report |
|
 |
1.8 Predesign
Deliverables |
| |
|
| |
1.8.1
|
Submit 100% Draft
Predesign Documents for review:
|
| |
|
| |
1.8.2 |
Resolve Predesign Review Comments and Submit
Final Predesign Documents
Resolve all review comments and incorporate resolutions into
the Final Predesign Documents. Submit the Final Predesign Documents
and written responses to review comments, utilizing the NPS review
form, within 15 calendar days of receipt of comments.
Back to top ^
|