Safety Quality Assurance Checklist
Predesign
- Required deliverables submitted
Schematic Design
- Required deliverables submitted
- NPS Safety (NPS Director’s Order [DO] 50B) and Fire Protection (DO 58) standards identified
- Outline Fire Protection and Life Safety Plan (NPS Reference Manual [RM] 58)
- Identify all applicable Codes and Standards, including Building Code
Design Development
- Required deliverables submitted
- NPS Safety (DO 50B) and Fire Protection (DO 58) standards followed
- Identified Codes and Standards, including Building Code are used
- Draft Fire Protection and Life Safety Plan (RM 58)
- General Description
- General Construction Aspects
- Occupancy Classifications
- Fire Resistive Separations
- Doors and Windows
- Interior Wall, Ceiling and Floor Finishes
- Decorative Structures within Buildings
- Egress
- Special Design
- Emergency Signage
- Suppression Systems
- Fire Department Access
- Fire Detection and Alarm System
- Emergency Communication Systems
- Smoke Management Description
- Central Control Station
- Emergency and Standby Power
- Elevators
- Provide Fire Protection Plan(s) that graphically summarize key features as described in the Fire and Life Safety Plan
- Outline specs provided for all required sections
100% Draft Construction Documents or 100% Draft Design-Build Construction Documents
- Required deliverables submitted,
- NPS Safety and Fire Protection standards followed
- Final Fire Protection and Life Safety Plan
- Fire Protection Plan(s) that graphically summarize key features as described in the Fire and Life Safety Plan
- All required specification sections provided
Submit 100% Complete Construction Documents or 100% Complete Design-Build Construction Documents for Final Approval
- Required deliverables submitted
- All review comments from 100% Draft Review satisfactorily resolved