1.0 Approved Project Agreement

square bullet

1.1 Assign Planning Team

The Denver Service Center’s planning Division Chief assigns a Branch Chief and Project  Manager to the special resource study.  An interdisciplinary team of planning and resource professionals from the Denver Service Center is assigned to the special resource study.  Staff from the Regional office and the Denver Service Center planning team review the congressional legislation authorizing the special resource study.


square bullet

1.2 Prepare Project Schedule and Workload

Working collaboratively with the branch chief, the project manager develops a project schedule, including estimated dates for achieving key milestones, and a workload for the project (hours preliminarily allotted to members of the planning team for accomplishing assigned tasks).  The project schedule is included in project agreement.


square bullet

1.3 Prepare/Review Project Agreement

The project manager, in consultation with the branch chief, prepares a project agreement that (1) identifies the work to be accomplished and the project budget; (2) sets the schedule for completing the special resource study; and (3) defines the roles and responsibilities of the planning team as well as others in the regional office and Washington office who may be involved in preparation of the document. 


square bullet

1.4 Signed Project Agreement

The DSC’s planning division chief and the regional director sign the approved project agreement.  The project manager creates a listing for the SRS in the NPS’s Planning, Environment and Public Comment (PEPC) website.

 
bullet

1.0 Approved Project Agreement

bullet 2.0 Publish Notice of Scoping in Federal Register
bullet 3.0 Print Scoping Newsletter
bullet 4.0 Access National Significance, Suitability, and Feasibility
bullet 5.0 Print Preliminary Findings Newsletter
bullet 6.0 Publish NOI in Federal Register (May be Optional)
bullet 7.0 Internal Draft SRS/Environmental Document (EA or EIS)
bullet 8.0 Printed Draft SRS/Environmental Document (EA or EIS)
bullet 9.0 Publish NOA in Federal Register (May be Optional)
bullet 10.0 Complete Public Review of SRS/Environmental Document
bullet 11.0 Print Final SRS/Environmental Document
bullet 12.0 Publish NOA in Federal Register (May be Optional)
bullet 13.0 Record of Decision (May be Optional)
 
Information
DSC Workflows Definitions
Forms / Templates / Samples / Guidelines
Laws and Policies
Photo Gallery
What's New

Site Map | Contact | | Disclaimer | FOIA | US Department of Interior | USA.gov | ParkNet | DSC